Pennsylvania has awarded one of the four regional rounds in its federally funded Community Charging program. The other three are still open, and the first deadline is three days away. According to the Pennsylvania Department of Transportation (PennDOT), applications for the Western Region close on November 20, 2026. The Central and Eastern rounds both close on March 12, 2027.
Community Charging is the part of Pennsylvania's National Electric Vehicle Infrastructure (NEVI) Formula Program that funds public charging away from the designated highway corridors. The Southeastern Region awards were announced on October 28. This article covers the rest of the calendar: which rounds are open, when they close, and what an eligible station has to include.
The Calendar at a Glance
PennDOT's NEVI program page lists these dates for the four Community Charging rounds as of November 17, 2026:
- Southeastern Region: opened February 19, 2026; closed August 25, 2026; awards announced October 28, 2026. Status: awarded.
- Western Region: opened June 12, 2026; closes November 20, 2026. Status: open, three days remaining.
- Central Region: opened September 8, 2026; closes March 12, 2027. Status: open.
- Eastern Region: opened September 17, 2026; closes March 12, 2027. Status: open.
From opening to awards, the Southeastern round took a little over eight months: about six months of applications, then roughly two months of review. PennDOT has not published award dates for the other three regions. Its page sets closing dates only, so any estimate of when the Western, Central or Eastern awards will arrive would be a guess.
PennDOT lists [email protected] as the program contact on its NEVI page.
How Much Money Is Involved
PennDOT says Pennsylvania will receive $171.5 million in NEVI formula funding over five years. The AASHTO Journal reported that Pennsylvania is directing over $100 million in federal funding to community charging through its funding rounds. That is in addition to the $58 million already invested through the state's Alternative Fuel Corridors and Corridor Connections programs. Electrek also described the community charging effort as roughly $100 million statewide.
The Southeastern round used about $37 million of the community total. Subtracting that from "over $100 million" would leave roughly $63 million or more, if the $37 million is counted within that total, for the Western, Central and Eastern rounds combined. Neither PennDOT nor the coverage cited here gives a per-region split, and that remainder is ChargerFeed's arithmetic, not a published figure. Applicants should not assume the money will be divided evenly among the three regions.
What an Eligible Station Looks Like
Electrek summarized the program's minimum requirements. Each funded community charging station must have:
- At least four charging ports
- At least 6 kW per port
- Two ADA-accessible spaces
- A J1772 or CCS connector on every port
- Compliance with Buy America requirements
Electrek reported that the program supports both Level 2 and DC fast charging, and the Southeastern round funded both. The program rules are minimums, and they do not replace site-specific engineering.
The AASHTO Journal also described how sites qualify. Local planning agencies mark priority areas, but any publicly available location in a region is eligible to apply. The coverage cited here does not say how priority status affects scoring.
What the First Round Funded
The Southeastern awards show what the program has paid for so far. As reported by Electrek and the AASHTO Journal, PennDOT made 71 awards worth about $37 million for 515 new public ports across Bucks, Chester, Delaware, Montgomery and Philadelphia counties. Electrek reported that the awards will expand public charging by 27% across the region and 53% in Philadelphia. EV Infrastructure News covered the same awards and put the total at about 515 ports.
Award sizes and charger types varied widely. Electrek reported these awards:
- It's Electric PA: $2.93 million for 157 curbside Level 2 ports in 13 neighborhoods
- Voltpost: 62 curbside ports
- PositivEnergy: $7.2 million for 54 DC fast charging ports at 11 Philadelphia Parking Authority lots
- Tesla: two awards of $392,000 each, for 8 ports apiece at a Royal Farms in Broomall and a Wawa in Plymouth Meeting
These ports are funded, not built. The awards set aside money for the projects. Electrek reported that PennDOT's estimated schedule puts environmental reviews from November 2026 through January 2027 and agreement execution in January and February, with construction and commissioning still to follow. None of the reporting cited here says when the Southeastern sites will open. ChargerFeed's earlier coverage of the Southeastern awards has more on the individual projects.
Where Pennsylvania Stands on NEVI Overall
PennDOT says the Federal Highway Administration certified the state's corridor network as fully built out on September 22, 2025. That certification is what lets the state put its remaining formula money into community charging. As of PennDOT's current program page, the state has:
- 159 active NEVI projects in 46 counties
- $95.8 million in federal funding committed to those projects
- More than 50 NEVI-funded stations in operation
Electrek's count, published November 3, 2026, is 54 NEVI-funded stations built, which it said is more than double the number in any other state. PennDOT's "more than 50" and Electrek's 54 are consistent but come from different sources at slightly different times. The "active projects" figure combines stations that are open with stations still in development.
What It Means for Drivers
None of the open rounds adds a charger right away. The Western, Central and Eastern rounds are still taking applications. Drivers in those regions will not know which sites were selected until PennDOT announces awards, and the sources cited here do not give a date. After awards come construction and commissioning, and the sources cited here give no timeline for those steps either.
When stations open, the program minimums set some baseline expectations. Every funded site will have at least four ports, each port will deliver at least 6 kW, every port will have a J1772 or CCS connector, and there will be two ADA-accessible spaces. These are public stations. The Southeastern awards included curbside Level 2 ports in residential neighborhoods, DC fast charging at public parking lots, and chargers at convenience-store sites. The open rounds could fund a similar mix, but that will depend on who applies and what PennDOT selects.
In the five southeastern counties, the 515 funded ports are the nearer-term change. They are still announced and funded, not open. None of the sources cited here reported charging prices for the new sites. Drivers should check posted rates at each station once it opens.
Drivers on Pennsylvania's designated corridors are already covered by the build-out PennDOT finished under FHWA certification in September 2025. The community charging rounds are aimed at the places corridor stations do not reach, such as neighborhoods, parking lots and local retail sites. The AASHTO Journal reported that local planning agencies help decide where those sites go.
For Site Hosts: The Practical Takeaway
- Western Pennsylvania: the deadline is November 20, 2026. PennDOT's NEVI page describes Community Charging as a one-time opportunity and the sources cited here do not mention a future round.
- Central and Eastern Pennsylvania: there are about four months left, with both rounds closing March 12, 2027.
- All regions: plan for at least four ports, at least 6 kW per port, two ADA spaces, J1772 or CCS on every port, and Buy America compliance. A site does not need to be in a planning-agency priority area to apply.
Program details, including any changes to dates, are posted on PennDOT's NEVI page. The dates and counts in this article are as of November 17, 2026.
Sources
- PennDOT: National Electric Vehicle Infrastructure (NEVI) Formula Program
- Electrek: Pennsylvania is way ahead on NEVI charging, now comes another $37M (Nov. 3, 2026)
- AASHTO Journal: PennDOT Issues $37M for EV Chargers in Southeastern PA (Nov. 6, 2026)
- EV Infrastructure News: Pennsylvania to get 500+ public charging points as federal funds continue