The Washington State Department of Transportation (WSDOT) has put all of its remaining National Electric Vehicle Infrastructure (NEVI) formula money, about $69 million, into a single solicitation. Unlike Round 1, this one does not close on one date. Proposals can come in at any time until Oct. 20, 2027 according to WSDOT's grant page (the NOFO text says the window closes Oct. 19, 2027), and WSDOT will review them in monthly batches. The first evaluation deadline is in December 2026.

The Round 2 Notice of Funding Opportunity and Request for Proposals (NOFO/RFP) opened Oct. 20, 2026. The PDF was last updated Oct. 19, 2026. Since then WSDOT has held an informational webinar on Nov. 5, stopped taking questions on Nov. 6, and posted a Q&A document on its NEVI grant page. Applicants who wanted to be in the first review cycle now have the full set of materials. Here is what the program pays for, where, and what it requires.

The money, in numbers

  • About $71 million: Washington's total NEVI formula allocation for federal fiscal years 2022 through 2026, according to the NOFO.
  • About $69 million: the amount offered in Round 2, which the NOFO calls all of the state's remaining NEVI funds. WSDOT's grant page says Round 2 includes funds rolled over from Round 1.
  • Up to 80%: the largest federal share of eligible project costs.
  • 20% / 30%: the minimum applicant match. It is 20% for passenger-vehicle (light-duty) projects and 30% for medium- and heavy-duty (MHDV) projects.
  • 2,235 miles: the length of Washington's designated Alternative Fuel Corridors (AFCs), per the NOFO.
  • Five years: how long awardees must keep sites at 97% annual uptime.

WSDOT's grant page says $10,882,916 in proposed Round 1 awards was withdrawn and redirected into Round 2, which is part of why the $69 million includes rolled-over funds. The documents we reviewed do not give a full reconciliation of the $71 million and $69 million figures.

How the rolling process works

Round 1 used a standard single-deadline competition. Round 2 runs on a monthly cycle. WSDOT's grant page says it reviews the previous month's proposals each month, and the NOFO sets monthly evaluation deadlines from December 2026 through November 2027. Applicants that miss one cycle can submit for the next one. The program has a fixed amount of money, though, and the documents we reviewed do not say whether money will still be available in later cycles if early rounds award a large share of it.

The Atom Grants listing, a third-party aggregator and not a WSDOT source, describes the opportunity as open to shovel-ready projects only. It also says awardees must cover five years of operations and maintenance. Its dates match WSDOT's documents: questions closed Nov. 6, 2026, and rolling deadlines run to October 2027.

Two kinds of sites, two sets of specs

The NOFO divides Round 2 into two tracks with very different hardware requirements.

Light-duty sites on rural and low-traffic corridors

WSDOT wants passenger-vehicle fast-charging sites on these corridors:

  • US 2, US 12, US 97, US 101, US 195 and US 395
  • I-82 and I-90

Each site needs at least four ports that can deliver 150 kW at the same time. Sites should be 45 to 55 miles apart and within 5 miles of an exit. The NOFO also says WSDOT is not taking applications for I-205, I-405 or I-705, saying there is sufficient charging equipment along those highway extensions.

Medium- and heavy-duty sites on I-5

The second track is for medium- and heavy-duty vehicles: up to six truck-capable sites on I-5, spaced 50 to 75 miles apart. The NOFO's minimums for each site:

  • At least four 350 kW ports able to run at the same time.
  • Every port rated at 250 kW or more.
  • At least 2.5 MW of installed charging capacity.
  • Four pull-through ports, so a tractor-trailer can drive through instead of backing in.
  • Conduit, switchgear and a pad built for a future Megawatt Charging System (MCS) charger. This is provisioning only; the NOFO text provides for conduit, switchgear and a pad, not an MCS charger, at opening.
  • Site power of at least 80% of nameplate capacity (minimum 2 MW) at commissioning, increasing to 100% within five years.

The NOFO lets a site open with less than its full design power, but it must reach full power within five years. Any physical electrical work at these sites, as at any charging site, is for licensed electricians and utility engineers working to the equipment makers' specifications.

Uptime and interoperability rules

Every Round 2 site must keep 97% annual uptime for five years. Equipment and networks must support three industry standards:

  • ISO 15118, the vehicle-to-charger communication standard that supports Plug and Charge.
  • OCPP 2.0.1, the protocol between chargers and the operator's management software.
  • OCPI 2.2.1, the protocol for roaming and data exchange between charging networks.

The NOFO also says that federal minimum standards under Title 23 CFR Part 680 and Buy America requirements apply.

Round 1 context: what was awarded

On Jan. 29, 2026, WSDOT issued a notice of proposed awards for Round 1 to five companies (Electric Era, Energy Northwest, EV Gateway, EVgo and Tesla). EC&M reported on Feb. 3 that the awards totaled $12.16 million in federal NEVI funds for 14 stations along I-90, US 97, US 195 and US 395, with stations to be built within 24 months.

That total is out of date. WSDOT's grant page now carries a status update: after WSDOT and prospective awardees reviewed program requirements, only two Tesla sites, Moses Lake ($627,161) and Veradale ($648,750), are listed as proceeding to construction, for revised Round 1 awards of $1,275,911. The other proposed awards, including those for Issaquah, North Bend, Cle Elum, Ellensburg, George, Ritzville, Toppenish, Goldendale, Colfax, Pullman, Deer Park and Colville, are listed as withdrawn and not proceeding to construction. WSDOT says that funding, $10,882,916 in total, was released and is now part of Round 2 eligible funding.

None of the sources gave an opening date for any Round 1 site. The Round 1 corridors (I-90, US 97, US 195 and US 395) are all on the Round 2 light-duty list, which also includes US 2, US 12, US 101 and I-82, alongside the separate I-5 truck track.

What It Means for Drivers

Round 2 is a funding opportunity, so it puts no new chargers on the ground right away. The order of events is: proposals, monthly evaluations starting in December 2026, awards, then construction. None of the sources reviewed give a date for when a Round 2 site might open.

Passenger EV drivers on rural Washington highways are the main beneficiaries if projects are funded and built. The NOFO aims for fast-charging sites every 45 to 55 miles on US 2, 12, 97, 101, 195 and 395 and on I-82 and I-90, each within 5 miles of an exit and each with at least four ports able to deliver 150 kW together.

Drivers on I-205, I-405 and I-705 should not expect NEVI Round 2 sites there. WSDOT is not taking applications for those routes.

Truck and fleet operators on I-5 could get about six high-power sites 50 to 75 miles apart, each with pull-through ports and at least 2.5 MW installed. Sites that get funding are to include conduit, switchgear and a pad for a future MCS megawatt charger, but the NOFO does not require MCS hardware when a site opens. Passenger EVs could also use the 350 kW ports at these sites if a vehicle supports that power level, though the NOFO describes the sites mainly as MHDV infrastructure.

Reliability and payment: the 97% uptime requirement and the ISO 15118, OCPP 2.0.1 and OCPI 2.2.1 standards apply to every Round 2 site for five years. For drivers, that means the sites are designed to support Plug and Charge on compatible vehicles and roaming between networks. None of the sources set or disclose charging prices. Pricing will be up to individual operators and was not part of the documents reviewed.

Round 1 sites: as of WSDOT's grant page, only the Tesla sites in Moses Lake and Veradale are listed as proceeding to construction. The other locations first announced in January, such as Cle Elum, Ellensburg, Goldendale and Pullman, are listed as withdrawn. Check a station-finder app for current status before counting on any site.