The UK government's Depot Charging Scheme has confirmed the details of its second application window. Fleet operators now have a grant rate, a budget and fixed dates. According to the scheme's listing on GOV.UK's Find a Grant service, the window runs from 12:00 on 11 November 2026 to 12:00 on 26 February 2027. It has a £38 million budget and pays 60% of chargepoint and civil costs, capped at £1 million per organisation across all of its sites.

The window opened two weeks later than an earlier plan had indicated, and the grant rate is 10 percentage points lower than in the first round. Earlier guidance said the window would open on 28 October. This article sets out the confirmed terms and what changed between the two versions.

The Numbers, Then and Now

Guidance published on 29 May 2026 by NI Business Info described a £66 million plan split across two windows. Window one (2026/27) had £28 million and window two (2027/28) had £38 million. Window one paid 70% of eligible costs up to £1 million across all sites. It closed on 30 June 2026, or earlier if the money ran out. That guidance said window two would open on 28 October 2026 and close on 29 January 2027, and it said the grant rate had not yet been confirmed.

The current Find a Grant listing fills in those gaps:

Window 1 (2026/27)Window 2: earlier plan (NI Business Info, May 2026)Window 2: confirmed (Find a Grant, Nov 2026)
Budget£28M£38M£38M
Grant rate70%Not confirmed60%
Cap per organisation£1M across all sitesNot stated£1M across all sites
OpensNot stated in sources28 Oct 202611 Nov 2026, 12:00
Closes30 Jun 2026 (or earlier if exhausted)29 Jan 202726 Feb 2027, 12:00

The opening date moved back by 14 days and the closing date by four weeks. That makes the window longer overall: by ChargerFeed's count, about 107 days from open to close, compared with about 93 days under the earlier plan.

What 60% Means in Practice

The cap stays at £1 million, but because the grant rate is lower, an applicant has to spend more before reaching it. ChargerFeed's arithmetic, based on the published rate and cap: at 70%, the £1 million cap applied at around £1.43 million of eligible spend. At 60%, it applies at around £1.67 million. Below that level, each pound of eligible spend now attracts 60p of grant instead of 70p.

The £38 million budget would cover at least 38 organisations even if every award hit the £1 million maximum. In practice the number depends on project sizes, and the sources don't project an award count.

How Applications Will Be Judged

Find a Grant says each organisation may submit one application per window, though it can include any number of sites. Applications are assessed first-come, first-served, unless the window is oversubscribed, in which case they are assessed competitively. The listing names engineering consultancy WSP as the scheme's technical partner.

The listing also sets eligibility conditions. Applicants' fleets must include, or will include in future, at least one battery-electric van, HGV or coach, and applicants must own or lease one or more UK depots. They must consent to the primary users of the funded infrastructure being commercial vehicles. Drax Energy Solutions, a chargepoint vendor with its own page on the scheme, adds that a site cannot be applied for again within two years of completed works. That detail comes from a vendor page, not the government listing, so applicants should check it against the official scheme guidance.

Find a Grant gives a dated timetable: the government aims to conclude all award decisions by 28 May 2027, and funded projects must be complete by 31 March 2028. Drax repeats both dates. If the decision target holds, successful applicants will have about ten months from award to completion.

The Bigger Programme

According to Find a Grant, this window is part of a £170 million multi-year programme running from April 2026 to 2030. Further windows are expected for the 2028/29 and 2029/30 financial years. Their timing and grant rates are due to be confirmed in 2027. The listing says grant rates are anticipated to reduce over the lifetime of the programme as charging infrastructure becomes more affordable, which is consistent with the drop from 70% to 60% between the first two rounds. Rates for later windows have not been published.

To be precise about status: the £38 million for window two is a budget that is now open for applications. No awards from this window have been announced. The 2028/29 and 2029/30 windows are expected, and their terms have not been set.

What It Means for Drivers

This scheme funds charging at private depots, not public charging. It part-funds chargepoints and the civil works behind them at fleet depots, for battery-electric vans, HGVs and coaches. Find a Grant says the primary users of funded infrastructure must be commercial vehicles, and that if infrastructure is shared with other fleet operators, pricing must be based on cost recovery for at least three years after the grant is awarded. Neither source describes funded sites being opened to the public, so drivers of private cars should not expect new public chargers from this programme.

For drivers of fleet vans, trucks and coaches, the practical effect is on depot charging. Operators that win awards in this window will need to finish their installations by 31 March 2028, according to Find a Grant. Award decisions are targeted for 28 May 2027. So new depot chargepoints funded by this round are most likely to come into use between mid-2027 and early 2028, although each operator will set its own schedule within that deadline.

For fleet managers and site hosts, the key dates are:

  • 11 Nov 2026, 12:00: window opened (Find a Grant).
  • 26 Feb 2027, 12:00: window closes (Find a Grant). Under first-come, first-served assessment, applying early may matter if the budget fills before then.
  • 28 May 2027: government's target for concluding award decisions (Find a Grant; Drax).
  • 31 Mar 2028: funded projects must be complete (Find a Grant; Drax).

Depot chargepoint installations, including grid connections and civil works, should be designed and carried out by a qualified, licensed electrical contractor following the manufacturer's instructions. This article does not give installation guidance.

Bottom Line

Compared with the earlier plan, window two of the Depot Charging Scheme is open with the same £38 million budget, a confirmed 60% grant rate, the same £1 million cap per organisation, and dates that are two weeks later at the start and four weeks later at the close. The government has said it expects future rounds to pay a smaller share of costs, with terms to be confirmed in 2027.