Terawatt Infrastructure announced four fleet charging depots on Nov. 12, 2026: one each in South San Francisco, Nashville, Miami and the Dallas/Fort Worth area. The company gives their combined dedicated capacity as 22 megawatts. The four sites do not all have the same status, though. According to the company's release, two (South San Francisco and Nashville) are described as already supporting fleet operations. The other two (Miami and Dallas) were still scheduled to open "this quarter" when the announcement went out.

The number deserves a closer look. The body of the release says "22 megawatts (MW)," and the PR Newswire subhead says "nearly 22 MW." The four per-site figures Terawatt published (6.6, 4.5, 3.5 and 7 MW) add up to 21.6 MW. "About 22 MW" is a fair rounding. The real total is a little under that.

The four sites, by status

This is how Terawatt describes each depot, as of its Nov. 12, 2026 announcement:

SiteCapacityLocation detailStatus per release
South San Francisco, Calif.6.6 MWNear San Francisco International Airport (SFO)Buildout completed; supports one fleet's Bay Area operations
Nashville, Tenn.4.5 MWNear Nashville International AirportDescribed as supporting local fleet operations
Miami, Fla.3.5 MWDesign District / Wynwood area"Opening this quarter" (not yet open at announcement)
Dallas/Fort Worth, Texas7 MWNear DFW Airport"Will go live this quarter" (not yet open at announcement)

Split that way, 11.1 MW of the 21.6 MW total was described as operating when Terawatt made the announcement, and 10.5 MW was scheduled. The largest site, the 7 MW depot near DFW, is in the scheduled group. ElectricDrives, an independent trade outlet, reported the same split in its Nov. 12 coverage. It called the Dallas site the largest of the four and listed both Dallas and Miami as opening this quarter.

Terawatt says the four depots together can charge "more than 3,000 vehicles per day." That is the company's own capacity estimate, and ElectricDrives described it as "in theory" enough for that volume. Neither source gives utilization data for the sites.

Built faster and cheaper, according to Terawatt

The release goes into the most detail on South San Francisco. Terawatt says it completed that buildout ahead of schedule and reduced costs "by six figures" through site-energization methods and close collaboration with Pacific Gas & Electric Company (PG&E). The company does not give a total project cost, a baseline the savings were measured against, or the methods it used. Readers should treat the claim as a company statement that has not been independently quantified.

The PR Newswire version of the release lists what Terawatt handled itself across the projects: development, construction, entitlements, utility interconnection and site design. It also says Terawatt will run charger operations and maintenance at the depots using its own Charge Management Software. The release describes Terawatt's depots as turnkey and fully built out, unlike "powered land" models that leave site construction to the operator.

Who is using them

The release does not name the fleets using the four depots. At South San Francisco it refers only to "one fleet's" Bay Area operations, at Nashville to "local fleet operations," and at Miami and Dallas to "a commercial fleet operator." The company boilerplate names Waymo and Flexdrive by Lyft as clients Terawatt serves in general. It does not tie either one to any of these four sites, and this article does not either.

The broader pipeline

Terawatt says these sites join its network of nearly 30 depots in active construction or development across 16 US markets, and CEO Neha Palmer says there are "more on the way in 2027." The company says its network has delivered more than 93 million miles of clean driving range and dispensed more than 30 million kWh. Those are company-reported cumulative figures. The release does not say how many of the nearly 30 sites are under construction and how many are still in development, and it gives no opening dates for them.

The release quotes Palmer, and ElectricDrives quotes her as well. On policy, ElectricDrives notes that many EV-related incentives have been dropped by the current administration. Neither source says whether that change affected the financing or timing of these four depots.

What It Means for Drivers

These are fleet depots. The release describes them as dedicated charging capacity for commercial fleets, and neither source describes the four sites as open to the public. A private EV driver should not expect to pull into any of these locations and plug in. The release does not mention public access, pricing or charger connector types, and it gives no per-kWh or per-minute rates.

For people who drive for or manage fleets, this is what the sources say, as of Nov. 12, 2026:

  • Bay Area (South San Francisco, near SFO): A 6.6 MW depot supports one unnamed fleet's Bay Area operations.
  • Nashville (near Nashville International Airport): A 4.5 MW depot supports local fleet operations.
  • Miami (Design District/Wynwood): A 3.5 MW depot is scheduled to open this quarter. It was not open when Terawatt made the announcement.
  • Dallas/Fort Worth (near DFW Airport): A 7 MW depot is scheduled to go live this quarter. It was not open when Terawatt made the announcement.

Terawatt does not name the specific vehicle types or uses at each site. Fleet operators who want depot access would need to contact Terawatt directly. The sources do not describe contract terms or say whether any capacity is still available.

Site hosts and depot operators weighing their own charging projects should note that the release describes the electrical and utility work only in general terms. Any on-site charging installation should be designed and built by a licensed electrician, following the equipment manufacturer's instructions and the local utility's interconnection requirements.

What to watch

The quarter ends Dec. 31, 2026. Whether the Miami and Dallas/Fort Worth sites open on schedule decides whether Terawatt's "22 MW" is fully operating by year-end or still partly planned. The other number to watch is how many of the nearly 30 depots in construction or development move to operation in 2027.