EV Realty announced on Nov. 17, 2026 that it has started building a heavy-duty truck charging hub at 18715 S. Western Avenue in Torrance, California. The company describes the site as 9 MW with 50 high-power ports, offering both the Megawatt Charging System (MCS) and CCS connectors. The site is a construction project, not an open station. The company is targeting commercial operation in mid-2027.

The project is called the South Bay Truck Charging Hub in state paperwork. A signed baseline agreement with the California Transportation Commission (CTC) gives more detail than the press release. It lists the scope, the funding and the schedule that the state's money depends on.

The Numbers, Side by Side

The company release and the state agreement mostly agree, but they describe the hub in different ways.

  • Charger count: EV Realty's release says 50 high-power ports. The CTC agreement, signed May 15 and June 2, 2026, lists 30 pull-in DC fast chargers rated up to 350 kW and 20 DC fast stalls rated up to 1,200 kW with MCS ports. That also adds up to 50, with 20 of them megawatt-class.
  • Site power: 9 MW, per the company and the CTC agreement.
  • Total cost: $22.12 million, per the CTC agreement. That is $7.9 million from the state's Trade Corridor Enhancement Program (TCEP) plus $14.215 million in leveraged (non-TCEP) funds.
  • Schedule: The CTC agreement sets groundbreaking in Q4 2026 and operation in 2027. The company now says mid-2027 for commercial operation. Both dates are projections.
  • Access: The CTC agreement says the hub will be open 24/7 to contracted fleets, including owner-operators.

The per-charger ratings are maximums. If you add up the CTC figures (30 chargers at up to 350 kW plus 20 stalls at up to 1,200 kW), you get 34.5 MW, well over the 9 MW the company quotes for the site. In practice, power will be shared, and not every stall can draw its full rating at the same moment. The sources do not say how EV Realty will split power across stalls at Torrance.

Why This Location

The site is right next to Interstate 405. The CTC agreement places it 1 to 2 miles from the I-110/I-405 and I-110/SR 91 junctions, close to the Ports of Los Angeles and Long Beach. The company's release says the hub will serve trucks working the San Pedro Bay port complex, inland distribution routes and air cargo at LAX.

The CTC agreement says the project is meant to serve drayage, regional haul and last-mile operations. Short drayage runs between the ports and nearby warehouses are the kind of work that battery-electric trucks could top up for during the day, though the sources do not describe specific fleet plans.

Who Is Paying

The company names three public funding sources:

  • CTC Trade Corridor Enhancement Program: $7.9 million, set out in the signed baseline agreement. The agreement names the developer as EV Western Tenant LLC, a subsidiary of EV Realty Holdings LLC.
  • Southern California Edison's Shared Fleet Charging Rebate Program: named by EV Realty as a backer. The release gives no dollar figure.
  • California Energy Commission EnergIIZE: a conditional award, per the company. The release does not give the amount or the conditions.

The CTC figure is the only public dollar amount in the sources. The $14.215 million in leveraged funds could include the utility rebate, the EnergIIZE award and company money, but the CTC document does not break it down.

EV Realty also names three project partners: ParWest, Synop and Outpost. The release does not spell out what each company is doing on the Torrance project.

Where It Fits in EV Realty's Network

EV Infrastructure News describes Torrance as EV Realty's second Southern California site. The status of each site, as of Nov. 17, 2026:

  • San Bernardino: a 9 MW hub, opened in April 2026.
  • Torrance: under construction as of Nov. 17, 2026, targeted for mid-2027.
  • Ontario, CA: planned, per the company.
  • Stockton, CA: planned, per the company.

The company says it is on track to have more than 100 MCS ports across Southern California by mid-2027. That is a goal, not a count of installed hardware. The CTC scope lists 20 MCS stalls at Torrance, which would count toward that goal if built as described.

Chief Commercial Officer Suncheth Bhat and CEO Patrick Sullivan are both quoted in the release. Their comments are about the company's plans and do not add specifications beyond those listed above.

What It Means for Drivers

Nobody can charge here yet. As of Nov. 17, 2026 the Torrance site is a construction project. EV Realty is targeting commercial operation in mid-2027, and the CTC agreement says only "2027." Fleets should not plan routes around it until the operator confirms an opening date.

It is a fleet site, not a public station. Under the CTC agreement, the hub will be open 24 hours a day, 7 days a week to contracted fleets, including owner-operators. A passenger EV driver should not expect to pull in and pay by card. Independent truckers can get access, but through a contract with the operator, not as walk-up customers. The agreement also lists basic driver amenities: bathrooms, security, lighting and on-site parking for drivers' personal vehicles.

Both connector types. The plan includes MCS for megawatt-class trucks and CCS. According to the CTC document, the 30 standard chargers top out at 350 kW and the 20 MCS stalls at 1,200 kW. Actual charging speed will depend on the truck, the battery's state of charge and how the site shares its 9 MW among stalls in use.

Pricing is unknown. None of the sources give a per-kWh, per-minute or subscription price for Torrance. Fleets interested in access will have to get contract terms from EV Realty directly.

The location targets port drayage. For trucks running between the San Pedro Bay ports, I-405, I-110 and inland warehouses, the site is 1 to 2 miles from two major freeway junctions, according to the CTC agreement.

What to Watch

The CTC agreement ties public money to a schedule: groundbreaking in Q4 2026, now reported as under way, and operation in 2027. The next things to check are whether the conditional EnergIIZE award is finalized, whether the operator publishes contract pricing, and whether the site opens with all 50 ports or in phases. ChargerFeed will update the status when the hub moves from under construction to operating.

Sources