The City of Covington, Kentucky, has published a site-by-site schedule for public EV charging. It covers three city parking garages and three future DC fast-charging locations. The city's Nov. 17, 2026 announcement came through the Covington Motor Vehicle Parking Authority (CMVPA). It separates what drivers can use now from what is planned.

As of Nov. 17, 2026, the count is five Level 2 units open in two garages and two more Level 2 units expected this month. Eight DC fast-charging (DCFC) units are planned at three sites. Six of them are scheduled for June 2027 and two for 2028. The city says installation and activation dates may be adjusted as work progresses and utility coordination is completed.

The Schedule, Site by Site

The table below follows the city release. Status is as of Nov. 17, 2026.

SiteAddressTypeUnitsStatus
John R. Green Garage604 Bakewell St.Level 22Open
River Center Garage100 Madison Ave.Level 23Open (activated Sept. 2026)
Midtown Garage501 Scott St.Level 22Expected November 2026
Latonia36th St. and Decoursey Ave.DCFC2Planned, June 2027
New City Hall630 Scott Blvd.DCFC4Planned, June 2027
MainstrasseLocation not yet setDCFC2Planned, 2028; site pending a Duke Energy review of the best available power supply

Two points in the table matter most. First, the City Hall site would be the first public DC fast charging in downtown Covington. The city also says these will be the first publicly available Level 3 stations in the downtown areas of Cincinnati, Covington or Newport. That claim comes from the city, and ChargerFeed has not checked it independently. Second, the Mainstrasse site is the least certain item on the list. The city has not chosen a location, and it says the location is pending Duke Energy's review to determine the best available power supply.

What the Sources Don't Say

None of the sources ChargerFeed read give power ratings, connector types, the charging network operator or prices for any site. ChargerFeed is not reporting any per-kWh, per-minute or parking-plus-charging rate, because none has been published in these sources. Drivers should check the posted rates at each garage or in the network's app before plugging in.

The release includes comments from CMVPA Executive Director Jack Monts de Oca. The facts above come from the city's published schedule rather than from those comments.

A Timing Wrinkle

The sources describe the fast-charging timeline in slightly different terms. WKRC Local 12 reported on Nov. 18 that two garages have Level 2 charging now and two more will have it by the end of the year. It also said the first public Level 3 stations would arrive "next spring" at Mainstrasse, City Hall and Ritte's Corner in Latonia.

The city's release uses similar wording in its opening, saying the CMVPA plans to introduce DCFC stations beginning in spring 2027 at Ritte's Corner in Latonia, the new City Hall and Mainstrasse. Its detailed location list is more specific: June 2027 for Latonia (36th St. and Decoursey Ave.) and City Hall, and 2028 for Mainstrasse. The list also shows one Level 2 garage, Midtown, as coming in November 2026. ChargerFeed is using the city's detailed list for the table. The Mainstrasse fast chargers are the item where the general "spring" wording and the 2028 date in the list differ most, so drivers should watch for city updates there.

How the Program Was Financed

The project's funding history helps explain why the work is happening in phases. In June 2026, LINK nky reported that Covington planned to seek federal funding. If approved, the funds would be passed through the Kentucky Transportation Cabinet from the Ohio, Kentucky, Indiana Regional Council of Governments (OKI) to the city on a reimbursement basis. The city could request reimbursement of up to $100,000 for the design phase and up to $500,000 for the installation phase. At that point the authority had picked three sites: River Center Garage, Midtown Garage and the Pershing Lot in Mainstrasse.

That report described a request not yet approved. ChargerFeed's sources do not say how much was awarded or how the current schedule is paid for. They also do not say whether the Pershing Lot is still being considered for the Mainstrasse fast chargers. The city release says only that the Mainstrasse location is pending.

What It Means for Drivers

Now (as of Nov. 17, 2026): Public Level 2 charging is available at the John R. Green Garage (604 Bakewell St., two units) and the River Center Garage (100 Madison Ave., three units). River Center's units were installed and activated in September 2026. The city describes Level 2 charging as well suited to places where drivers can leave their vehicles parked for longer periods, including public parking garages. That makes it a fit for an office day, a dinner or an event downtown.

This month: The Midtown Garage at 501 Scott St. is anticipated to add two Level 2 units in November 2026. Check that they are working before you rely on them.

June 2027, if the schedule holds: DC fast charging is planned at two sites. Latonia, at 36th St. and Decoursey Ave., would get two units. The new City Hall at 630 Scott Blvd. would get four. The city says the City Hall units are planned to be the first public DC fast chargers in downtown Covington. The city describes DC fast charging as the fastest commonly available charging method, with speeds that vary by vehicle and battery.

2028: Two DC fast-charging units are planned for Mainstrasse. The exact site is pending Duke Energy's review to determine the best available power supply.

What's still unknown: The sources give no prices, no charging speeds for specific sites and no network operator. For the garages, LINK nky reported in June 2026 that drivers using the lots and garages would be responsible for any charging-station fees as well as any fees to access the lots themselves. Whether that applies unchanged to the new sites is not confirmed. Each planned date is a target, and the city says dates may be adjusted.

Site hosts and fleet operators who are thinking about chargers near these locations should know that the city is already relying on a utility power-supply review for one site. Any private installation needs its own utility coordination and a licensed electrician who follows the equipment maker's instructions.