Australia has nearly 8,000 service stations, according to the Grattan Institute, but as of November 2026 it has no open-access charging network for heavy electric trucks. A new Grattan report, Fuelling the future, released around November 22–23, 2026, recommends that the federal government co-invest A$1.1 billion (about US$760 million) in public charging for electric trucks. On top of that it proposes A$2.4 billion in vouchers to help operators buy electric trucks.

Before going further, one point matters most. This is a policy recommendation from an independent think tank. No government has announced, budgeted or funded it. Everything below describes what Grattan proposes and what its analysis says, as reported in coverage of the report. Grattan's own web pages returned access errors when ChargerFeed tried to load them, so we could not read the report directly. The figures here come from the news reports listed at the end.

The Starting Point: Under 2,000 Electric Trucks

EV Infrastructure News, reporting on the study, says fewer than 2,000 of Australia's 830,000 trucks are electric. In 2025, electric models made up 0.8% of new truck sales in Australia. In China the figure was 29%.

Grattan frames the issue as fuel security as much as emissions. According to the same coverage, Australia imports 97% of the 60 billion litres of liquid fuel it uses each year. SSBCrack News notes that the country has only two oil refineries left.

Without new policy, Grattan forecasts only about 100,000 electric trucks in a fleet of 1.6 million by 2050, according to EV Infrastructure News. Its target with the proposed package is 650,000 electric trucks by 2050, a figure reported by the New England Times and SSBCrack News. The New England Times reports that this would cut diesel use by about 5 billion litres a year. EV Infrastructure News gives the fleet under the plan as about 670,000 by 2050 and the same 5 billion litre saving. ChargerFeed could not check the discrepancy against Grattan's own document, so this article uses the 650,000 target stated in two of the reports.

What the A$1.1 Billion Would Buy

The core proposal is government co-investment in an open-access network. That means charging sites any truck operator can use, as opposed to private depot chargers that serve one fleet. According to EV Infrastructure News:

  • A separate national assessment identified 165 locations where charging hubs would be needed for a mostly electric truck network.
  • Grattan estimates each hub would cost about A$26 million, assuming 20 bays: four with 100 kW chargers, eight with 400 kW chargers and eight with 1,000 kW chargers. The costing includes grid connection, transformers, electrical and civil works, a 12% contingency and 7% for design, but excludes land.
  • Across all 165 sites that comes to about A$4.2 billion, which Grattan expects the private sector to pay for most of. It recommends the government meet no more than half of the capital cost, and estimates A$1.1 billion would unlock half the chargers needed in each state.
  • Co-investment would begin on the busiest freight corridors, such as around the capital cities and along the Hume Highway, before extending to routes where the economics are weaker.

Our own multiplication of 165 sites at A$26 million gives about A$4.3 billion, slightly above the reported A$4.2 billion, which is likely rounding in the report. Readers should treat the per-site figure as an estimate, not a fixed program cost.

Grattan expects most truck charging to happen overnight at operators' own depots, which it says would host about seven in 10 chargers and two-thirds of charging demand. The gap the report identifies is on the road, for long-haul trucks and those that do not return to a depot each night.

The Rest of the Package

Chargers are one part of a wider set of recommendations. The New England Times reports that the report, led by author Alison Reeve, also calls for:

  • A$2.4 billion in vouchers to help trucking firms buy electric trucks. EV Infrastructure News describes them as covering half the price gap for the first 75,000 electric trucks sold from 2027, costing about A$2.4 billion by 2034.
  • A cap on diesel fuel tax credits of A$35 million per corporate group per year. SSBCrack News says the scheme's biggest beneficiary is the mining sector, and that Grattan suggests savings from the cap could fund the proposed A$6 billion of support for clean-fuel refineries. The Minerals Council of Australia has rejected the cap.

The voucher proposal is a response to the price gap Grattan expects. EV Infrastructure News reports Grattan's estimate that the electric truck premium in 2027 will be about A$74,000 for a rigid truck and about A$230,000 for an articulated truck. These are forecasts for 2027, not current dealer prices.

Why the Running Costs Matter

The economic case in the report depends on operating costs. According to EV Infrastructure News, Grattan estimates that a B-double costs about 80 cents per kilometre to run on diesel, and about 40 cents per kilometre on electricity charged at a depot. At October 2026 pump prices of A$2.81 per litre, the diesel figure rises to A$1.17 per kilometre. These are Grattan's estimates as reported in November 2026, and the electric figure assumes depot charging, not public fast charging.

That assumption is important for public infrastructure. Public high-power charging typically costs more per kWh than off-peak depot supply, so the gap per kilometre on a public network could be smaller than the depot comparison shows. The coverage ChargerFeed reviewed does not include a Grattan estimate of public truck charging prices.

What Exists Today, and What Is Only Planned

Here is where things stand as of late November 2026, based on the sources:

  • Under construction: NewVolt's heavy-vehicle charging hub at Laverton North in Melbourne's west, described by Grattan as the first open-access heavy vehicle charging site. It broke ground in August 2026 and, according to the report, is due to open at the end of 2026. It is expected to support more than 100 charging sessions a day. It is not yet open.
  • Selected for a federal program: New Energy Transport's Wilton depot south-west of Sydney, designed for up to 50 heavy electric trucks, has been selected for the federal government's Investor Front Door programme, according to EV Infrastructure News. A depot is not the same as an open-access public site.
  • Planned: New Energy Transport also plans to deploy six mobile units, each pairing a 640 kW charger with a 125 kWh battery, along NSW freight corridors by the end of 2026.
  • Proposed only: Grattan's A$1.1 billion charging co-investment and A$2.4 billion voucher scheme.

What It Means for Drivers

For truck drivers and fleet operators: per Grattan, no open-access network for heavy electric trucks is operating in Australia today. Charging an electric truck currently largely means charging at a depot. The first open-access option reported is NewVolt's Laverton North hub in Melbourne, and only once it opens, which is scheduled for the end of 2026. The mobile charging units planned for NSW corridors could add some on-route capacity if they arrive on schedule. Nothing in the Grattan report changes access in the short term, because it is a set of recommendations that governments may or may not take up.

For operators weighing a purchase: the vouchers and the charging co-investment are both proposals. Grattan's 2027 price premiums (about A$74,000 for rigid trucks and A$230,000 for articulated trucks) and its per-kilometre cost estimates are useful reference points. They are not quotes. Operators should get current vehicle and electricity pricing from suppliers. Anyone planning depot charging should hire a licensed electrician and follow the charger manufacturer's installation requirements.

For passenger EV drivers: the proposal is aimed at heavy vehicles. The sources do not say whether car drivers could use the proposed truck hubs.

For site hosts and utilities: Grattan's costing for each hub includes grid connection and transformers, and the report notes that upgrading a depot's grid connection can cost millions of dollars and take 18 to 24 months to approve. If any government adopts the plan, the reported figures imply about 165 high-power sites, which points to substantial grid-connection work at freight locations. No timeline, site list or funding round has been announced.

What to Watch

The next things to watch are whether the federal government responds to the report, and whether the Laverton North hub opens on its end-2026 schedule. The hub's actual usage will be the first real data on demand for open-access truck charging in Australia. Until a government commits funds, the A$1.1 billion co-investment is a costed proposal and nothing more.