The East London borough of Tower Hamlets has picked a company to build its next round of on-street EV charging. On Nov. 16, 2026, Tower Hamlets Council said it had appointed TotalEnergies to deliver more than 1,500 new fast charge points over the next four years. The council described the deal as the first LEVI-funded charging contract awarded in London.

The council says installation is scheduled to begin in December 2026 at Pritchards Road. As of the Nov. 16 announcement, the contract is a signed and announced commitment, and the council's release does not report any new points switched on under it.

Below are the numbers, what they include, and the points the announcement leaves open.

The deal in numbers

  • Supplier: TotalEnergies, appointed as the council's delivery partner.
  • Scale: more than 1,500 new charge points, according to the council.
  • Power level: AC charging at 22 kW, which the council calls "fast" charging.
  • Timeline: four years. The first installation is scheduled to begin in December 2026 at Pritchards Road.
  • Operating model: TotalEnergies will deliver and operate the charging infrastructure and supply the electricity. The council says electricity supplied through the network is sourced from 100% renewable generation.
  • Funding: LEVI. Buses and Local Transport Minister Simon Lightwood, quoted in the council's release, describes Tower Hamlets as receiving "a significant share of over £1.2 million in investment" supporting more than 1,500 fast chargers.
  • Status as of Nov. 16, 2026: contract awarded and announced; first installation scheduled for December 2026.

Where Tower Hamlets starts from

The contract adds to a network the borough has already grown quickly. The council says it has already delivered around 2,350 publicly accessible charge points. It also says that after installing more than 2,000 new chargers over the past 12 months, the borough moved from having the 19th to the 3rd highest concentration of public EV chargers in the country. Those figures come from the council's own Nov. 16, 2026 announcement.

The council links the need for public charging to housing. It says 93% of households in the borough lack access to off-street parking. For those residents, a home charger on a driveway is not an option, which is the council's case for a public charging network.

The scope grew: from 300-plus to 1,500-plus

The new announcement is much larger than earlier reporting on the same funding. The East London Advertiser reported earlier that Tower Hamlets Council had received £1.2 million from the Local Electric Vehicle Infrastructure (LEVI) Fund, in partnership with Barking and Dagenham Council. That report said the money would pay for more than 300 fast chargers over two years, with installation starting in early 2026. The same report said the borough has more than 5,400 registered plug-in vehicles and that the council had installed 2,000 charging points earlier in the year. The page's metadata dates it to October 2025, before the November 2026 announcement.

Compared with that earlier plan, the November announcement has about five times as many charge points and runs twice as long (four years instead of two). The funding figure in the new release, over £1.2 million as cited by the minister, is close to the earlier £1.2 million award. Neither source explains how the larger number of charge points will be paid for. The announcement doesn't break down how much comes from LEVI and how much from TotalEnergies or other sources. It also doesn't say whether the earlier 300-plus target was absorbed into the new contract or replaced by it, so the relationship between the two figures is unclear.

The council's 1,500 figure is also described inconsistently: its headline says "charging points," while the body of the release refers to "1500 fast charging sockets (AC 22kW)." The release does not say how many physical posts or bays this means.

How this differs from TotalEnergies' TfL rapid-charging deal

TotalEnergies already runs a lot of charging in London. Robert Fenech, Managing Director of TotalEnergies Charging Solutions UK, is quoted in the council's release as saying the company operates more than 3,200 charge points across London.

The Tower Hamlets contract is separate from the company's work with Transport for London. Zapmap reported in February 2026 that TfL had awarded TotalEnergies a contract to deliver up to 43 rapid or ultra-rapid chargers (100 kW and 200 kW) across London. Zapmap said TotalEnergies would provide and operate the chargers for 20 years with no financial cost to TfL, and described it as the second contract awarded to TotalEnergies for new EV charging points. The TfL sites are expected to be near key routes used by high-mileage commercial users, including taxis and freight, with many bays in south London, including Bromley, Lewisham and Sutton. Zapmap said delivery from that contract is anticipated to begin from the end of 2027.

The two contracts differ in scale and power level:

  • TfL contract: up to 43 rapid or ultra-rapid chargers (100 kW and 200 kW), which Zapmap says allow a recharge within 30 minutes.
  • Tower Hamlets contract: more than 1,500 AC points at 22 kW, according to the council.

A 22 kW AC point is a lower power level than a 100 kW or 200 kW unit, so the two programmes serve different charging needs. Neither source says how long a particular vehicle would take to charge at the new points, so drivers should check their vehicle's specifications.

What It Means for Drivers

Who it's for. The council presents the network as public charging for residents, businesses, taxis and private hire drivers, and cites the 93% of households without off-street parking as the reason it is needed. The points are described as part of the borough's public charging network, not private home chargers.

When things change. As of Nov. 16, 2026, the council's first scheduled installation is at Pritchards Road, beginning in December 2026. The network is to expand progressively across the borough over the following four years. The announcement does not give a full list of sites or a schedule for when each will be built and switched on. Drivers should treat any particular street as planned, not available, until a point shows as live.

What kind of charging. The council describes the new points as fast AC charging at 22 kW. That is a lower power level than the 100 kW and 200 kW rapid chargers in the separate TfL programme.

What it costs. Neither the council's announcement nor the other sources listed here give tariffs for the new Tower Hamlets points. No per-kWh or per-minute rate had been published in these sources as of Nov. 16, 2026. Drivers should check the tariff at the charge point or in the operator's app before plugging in.

Who runs it. According to the council, TotalEnergies will deliver and operate the charging infrastructure and supply the electricity, and the council appointed it as its delivery partner.

What to watch

  • Whether the Pritchards Road installation starts in December 2026 as scheduled, and when those first points go live.
  • Whether the council publishes a list of planned sites and a schedule for switching them on.
  • How the 1,500-point scope is funded, given the £1.2 million LEVI figure and the earlier plan for 300-plus chargers.
  • Published tariffs for the new points once they open.
  • Whether other London boroughs award their own LEVI contracts, given Tower Hamlets' statement that it awarded the first in London.